The Minister of Transportation, Mr Rotimi Amaechi, on Tuesday said that the official launching of Abuja-Kaduna rail project Won’t be Ready on May 29.

Amaechi disclosed this at Idu, Abuja, while inspecting the arrival of two new coaches by the contractors, China Civil Engineering Construction Company (CCECC).

READ ALSO  9 perish in auto crash in Enugu

He said that the development was due to earlier refusal of Daughters of Charity Hospital in Kubwa to relocate for the alignment of the rail track.

READ ALSO  Nigeria second highest HIV infected country in Africa

The minister however said that negotiation had been completed with the hospital, adding that a new facility, including a convent, would be built for them by the contractors on a new site.

READ ALSO  Tikari Danjuma's Appointment: Usani endangering regional security - Egbesu United